Follow the progress of the new Oskomera building

Week number 2 - January 2011

Ground work, laying foundations and installation of the steel structure.

Week number 2 - January 2011 (1/77)

Week number 2 - January 2011

Ground work, laying foundations and installation of the steel structure.

Week number 2 - January 2011 (2/77)

Week number 2 - January 2011

Ground work, laying foundations and installation of the steel structure.

Week number 2 - January 2011 (3/77)

Week number 3 - January 2011

The building is getting more and more in shape and the big size is already visible. Installation of steel structure company hall and inner walls.

Week number 3 - January 2011 (4/77)

Week number 3 - January 2011

The building is getting more and more in shape and the big size is already visible. Installation of steel structure company hall and inner walls.

Week number 3 - January 2011 (5/77)

Week number 3 - January 2011

The building is getting more and more in shape and the big size is already visible. Installation of steel structure company hall and inner walls.

Week number 3 - January 2011 (6/77)

Week number 4 - January 2011

Installation of the steel structure and inner walls of the company hall.

Week number 4 - January 2011 (7/77)

Week number 4 - January 2011

Installation of the steel structure and inner walls of the company hall.

Week number 4 - January 2011 (8/77)

Week number 4 - January 2011

Installation of the steel structure and inner walls of the company hall.

Week  number 4 - January 2011 (9/77)

Week 8 - February 2011

Brick work is applied

Week 8 - February 2011 (10/77)

Week 8 - February 2011

Overview of the steel structure in the company hall and warehouse

Week 8 - February 2011 (11/77)

Week 8 - February 2011

Steel structure on the 2nd floor

Week 8 - February 2011 (12/77)

Week 8 - February 2011

Offices and reception on the ground floor

Week 8 - February 2011 (13/77)

Week 8 - February 2011

East façade in the making

Week 8 - February 2011 (14/77)

Week 11 - March 2011

On site one is working very hard!

Week 11 - March 2011 (15/77)

Week 11 - March 2011

The production and logistics facilities become visible

Week 11 - March 2011 (16/77)

Week 11 - March 2011

The steel structure of the final production hall is installed

Week 11 - March 2011 (17/77)

Week 11 - March 2011

The steel structure of the final production hall is installed

Week 11 - March 2011 (18/77)

Week 11 - March 2011

The east side of the building; the offices

Week 11 - March 2011 (19/77)

Week 11 - March 2011

The main entrance at the south side near the water

Week 11 - March 2011 (20/77)

Week 11 - March 2011

Meanwhile the installation of the curtain wall at the south side of the building has been started

Week 11 - March 2011 (21/77)

Week 11 - March 2011

The brick work at the west side of the building is progressing steadily

Week 11 - March 2011 (22/77)

Week 14 - April 2011

Steel structure installed

Week 14 - April 2011 (23/77)

Week 14 - April 2011

Installation of the roof steel

Week 14 - April 2011 (24/77)

Week 14 - April 2011

Installation of the roof steel

Week 14 - April 2011 (25/77)

Week 14 - April 2011

Curtain wall of the south façade has been installed

Week 14 - April 2011 (26/77)

Week 14 - April 2011

Brick work well under way

Week 14 - April 2011 (27/77)

Week 14 - April 2011

Brick work well under way

Week 14 - April 2011 (28/77)

Week 14 - April 2011

Meanwhile second floor reached

Week 14 - April 2011 (29/77)

Week 14 - April 2011

Meanwhile reached the second floor

Week 14 - April 2011 (30/77)

Week 18 - May 2011

Curtain wall production facility Steel department is installed

Week 18 - May 2011 (31/77)

Week 18 - May 2011

Curtain wall production facility Steel department

Week 18 - May 2011 (32/77)

Week 18 - May 2011

Production facility Steel department under construction

Week 18 - May 2011 (33/77)

Week 18 - May 2011

Concrete is poured in the Logistics department

Week 18 - May 2011 (34/77)

Week 18 - May 2011

Concrete is poured in the Logistics department

Week 18 - May 2011 (35/77)

Week 18 - May 2011

Meanwhile in the department of Logistics the concrete is poured

Week 18 - May 2011 (36/77)

Week 18 - May 2011

Entrance of the building under construction

Week 18 - May 2011 (37/77)

Week 18 - May 2011

Production facility Façades

Week 18 - May 2011 (38/77)

Week 18 - May 2011

Installation of the windows at the East side of the building

Week 18 - May 2011 (39/77)

Week 18 - May 2011

East side of the building with the company restaurant on ground floor

Week 18 - May 2011 (40/77)

Week 24 - June 2011

The sliding door on the terrace at the second floor has been installed.

Week 24 - June 2011 (41/77)

Week 24 - June 2011

The sliding door of the restaurant on the ground floor is almost ready.

Week 24 - June 2011 (42/77)

Week 24 - June 2011

The East side façade is progressing steadily. The installation of the curtain wall is well under way.

Week 24 - June 2011 (43/77)

Week 24 - June 2011

Also the curtain wall above the main entrance of the building becomes visible.

Week 24 - June 2011 (44/77)

Week 24 - June 2011

The South side façade is almost ready.

Week 24 - June 2011 (45/77)

Week 24 - June 2011

The back side of the building, the logistics part, is being installed.

Week 24 - June 2011 (46/77)

Week 28 - July 2011

Mid July the TKI 262 façade equipped with LED-in-glass is installed.

Week 28 - July 2011 (47/77)

Week 28 - July 2011

The LED-in-glass system is supplied by our partner Saint Gobain Glass Solutions.

Week 28 - July 2011 (48/77)

Week 28 - July 2011

The windows are installed very carefully. In the glass you can already see the letters which will be lighted through the LED lights.

Week 28 - July 2011 (49/77)

Week 28 - July 2011

The East façade is being closed.

Week 28 - July 2011 (50/77)

Week 28 - July 2011

Even during the day from the inner side of the building the letters "Oskomera" are visible.

Week 28 - July 2011 (51/77)

Week 28 - July 2011

The lorry of Oskomera is used for the installation of the glass.

Week 28 - July 2011 (52/77)

Week 28 - July 2011

On the ground floor the entrance is visible in which a Utimal façade will be installed. This is a timber aluminium façade.

Week 28 - July 2011 (53/77)

Week 28 - July 2011

The building is becoming more and more beautiful!!

Week 28 - July 2011 (54/77)

Week 39 - September 2011

The LEDinglass façade which is realized together with partner Glassolutions Netherlands is almost completed

Week 39 - September 2011 (55/77)

Week 39 - September 2011

The green terrace at the second floor

Week 39 - September 2011 (56/77)

Week 39 - September 2011

Several people are working on the paving

Week 39 - September 2011 (57/77)

Week 39 - September 2011

The LEDinglass is tested

Week 39 - September 2011 (58/77)

Week 39 - September 2011

From the South side you have a look at the main entrance and the aluminium production

Week 39 - September 2011 (59/77)

Week 39 - September 2011

Now the aluminium production facility is not equiped yet you can experience the enormous size

Week 39 - September 2011 (60/77)

Week 39 - September 2011

The production facility steel was completed at the beginning of October

Week 39 - September 2011 (61/77)

Week 39 - September 2011

In the offices the glazed walls are installed

Week 39 - September 2011 (62/77)

Week 39 - September 2011

The equipment of the server room is a huge project

Week 39 - September 2011 (63/77)

Week 39 - September 2011

Because of the glazed walls the building is very transparant

Week 39 - September 2011 (64/77)

Week 39 - September 2011

The paving in front of the production facility steel and at the back ground the cycle shed under construction

Week 39 - September 2011 (65/77)

Week 39 - September 2011

At the East side you can see the personnel entrance

Week 39 - September 2011 (66/77)

Week 39 - September 2011

There is a void in the reception area

Week 39 - September 2011 (67/77)

Week 39 - September 2011

On all floors there are open-plan offices

Week 39 - September 2011 (68/77)

Week 39 - September 2011

From the landing you can overview the aluminium production

Week 39 - September 2011 (69/77)

Week 43 - October 2011

A nice view of the building that is almost completed

Week 43 - October 2011 (70/77)

Week 43 - October 2011

East façade with the personnel entrance

Week 43 - October 2011 (71/77)

Week 43 - October 2011

In the façade you can see the name Oskomera

Week 43 - October 2011 (72/77)

Week 43 - October 2011

Interior of the ware house

Week 43 - October 2011 (73/77)

Week 43 - October 2011

Production facility steel

Week 43 - October 2011 (74/77)

Week 43 - October 2011

One of the open-plan offices on the first floor

Week 43 - October 2011 (75/77)

Week 43 - October 2011

Landing in production facility façades

Week 43 - October 2011 (76/77)

Week 43 - October 2011

Main entrance

Week 43 - October 2011 (77/77)